A. Erosion control plans must be
certified by a professional engineer registered in the State of Iowa.
B. Erosion control plans must be reviewed and approved by the City Engineer.
C. Other local, state and federal permits may be required, depending on the
circumstances. It shall be the responsibility of the Engineer of Record to
acquire all applicable permits. A copy of all permits shall be provided to the
City Engineer before construction.
10.02 THRESHOLDS
A. Residential developments consisting of subdivisions and resubdivisions larger
than one acre in size will require an erosion control plan.
B. Commercial and industrial developments greater than one acre in size will
require an erosion control plan.
10.03 REQUIREMENTS
A. Erosion control plans shall be designed with the following general goals in
mind:
1. To protect the site from the significant loss of soil and top soil due to
erosion.
2. To protect downstream properties and facilities from the deposition of
sediments.
3. To protect onsite facilities and public improvements from damages due to
erosion.
4. To protect water quality.
B. The erosion control plans will designate an individual, including name,
title, address and phone number, to be responsible for the following duties
throughout the duration of the project:
1. Initial installation of the erosion control measures specified by the erosion
control plan.
2. Site inspections on a weekly basis and after rains greater than ¼" to assess
the effectiveness of existing erosion control measures and to direct
installation of additional erosion control measures in response to problems
noted during said inspections. The designated individual will keep a log of the
inspections and any corrective measures taken. No inspections are required while
the ground is frozen or there is snow cover. Inspections will resume when the
snow begins to melt. Inspections will continue until adequate ground cover is
established to control erosion.
10.04 METHODS
A. Methods of erosion control shall be consistent with those outlined in the
Iowa Construction Site Erosion Control Manual or other commonly accepted
engineering practices.
B. The plan shall include provisions for responding to unanticipated erosion
problems as they arise during the construction process.
C. Special care shall be taken to prevent erosion behind the curbs and beneath
the pavement of streets.